Significant progress this week despite the cold & the wet. (Photos are from this w/e- cold & dry)
All the blocks previously delivered are up & another big delivery was made last Friday.
We’re now seeing where the windows are going, little things like that!! And we can now be “inside” & get some idea of scale etc.
The only glitch is with the delivery of the very big windows for the lounge, which is delayed & which could get into the July/August holidays. We really hope not.
Some more photos.