There’s not too much to see, but outside the roof & 3 sides of the house are finished. The rear, north facing side is well on its way.
The outside area is being prepared for all the services, infill around the house, drainage etc using this neat bit of kit.
The inside has been cleared in preparation for the underfloor heating & then the thermic screed. Programmed to be installed this coming week.
All the internal electrics are protected too.
And lastly the electrician has started on the fuse box.
It’s started to rain at last. We need it, but just not right now.