Basically all the internal lime finishes & water proofing have been finished by Abigail & her final bill is paid.
The painter has to finish off the internal walls & ceilings.
The tilers have started tiling the showers & our toilet area but all to finish this coming week. Good to see the tiles up & we are happy with our choice. You never know!!
Some more electrics are in & the garage is completely finished. It just needs the shelving/racking to be fitted plus, of course, the door!
All the internal floors are completely polished & finished & have to dry over the weekend. They must now be seriously protected by everyone who goes in.
The 2 terrace floors & the garage are both finished as well.
This started on Wednesday & since then no-one other than the floor team was allowed inside the building or on the 2 terraces.
Because of this there’s no photos of the interior this week.
We’ll be the first in on Monday to see how it looks.
We’ve now got 9 working days to get everything installed.
Kitchens, cloakrooms, cupboards, bathrooms, etc etc. The carpenters will be there on Mon. We have some deliveries organised for Tues & Wed & the kitchen/bar area drawers, cupboards & surfaces will be installed Thur.
All the comms are up in the air with Orange suddenly trying to sort them out. We need a trench under the road (quel surprise!!) but we could be moving without comms! We first gave Orange all the info in March 2023 & they finally decided to act last week after much pushing & prompting & swearing from us.
Will we won’t we?? Everything crossed.
We’ve had awful weather – fog, rain, freezing fog, heavy frosts & glorious days.
This what it looked like this morning.
What will it look like on Monday?